Chilled Water Pump Installation
Table of contents
SCOPE AND PURPOSE
This "Method Statement" covers the on-site installation of CHILLED WATER PUMPS and the requirements of checks to be carried out.
REFERENCE DOCUMENTS
· Project Specifications
· Approved shop drawings (latest revision)
· Approved material submittals
GENERAL
Chilled water Pumps are generally to be installed in locations shown in drawings in the Plant Rooms.
EQUIPMENT
· Drilling Machine
· Spirit Level
· Lifting Equipment (Cranes)
· Scaffolding
· Hand tools of Tradesmen
· Alignment tools
RESPONSIBLE PERSONNEL
· Project Engineers
· Construction In-Charge.
· Site Engineer/Site supervisor.
· QA/QC Inspectors.
· Safety officer
· Site Foremen.
· Pipefitters
· Helpers
METHOD OF PRE-INSTALLATION
- Ensure that the approved material required to carry out work is available.
- Check the nameplate details of the Chilled Water Pump as per the approved shop, drawing/schedules, and material submittals before installation.
- Prior to the commencement of work, the area and access will be inspected to confirm that the site is ready to commence the work.
- The site engineer will check all relevant documentation and material applicable to a particular section of work before commencement.
- Physical verification of material will be carried out for any damages prior to taking it from stores.
- The site engineer/supervisor will give the necessary instructions to the tradesman and provide the necessary construction/shop drawings.
- The site engineer/supervisor will also check that the tools and equipment available are in compliance with contract requirements.
- The site supervisor is to explain to tradesmen regarding the safety precautions to be observed.
METHOD OF INSTALLATION
- Prior to the commencement of work, coordination will be done with other services.
- Make sure that the Pumps are free from damage and that all internal components are complete and in good condition.
- Chilled Water pump assemblies will be transported to the nearest point of erection. Care will be taken while handling the units to avoid Damage/distortion.
- Ensure that the foundations of the Chilled Water Pumps are as per the approved shop drawing.
- Install the Inertia base assembly on the foundation as per the approved shop drawing. Ensure the orientation, axis, and level of inertia base are as per the approved shop drawing.
- Fix the vibration isolators to the inertia base as per the approved shop drawing. Ensure that the locations match with the Chilled Water Pump base anchoring details.
- Complete the concrete filling in the Inertia base as per the approved shop drawing.
- Concreting for the Inertia base will be carried out by the Main Contractor.
- Install the chilled water pumps on the inertia base with vibration isolators connected to the chilled water pump base frame.
- Ensure the orientation axis and level of the pump as per the approved shop drawing.
- Ensure that the pump and motors are properly aligned.
- Complete the piping connections, including Valves and accessories/flexible connections to pump suction and discharge sides as per the approved shop drawing.
- Piping connections shall be erected to allow access to the operation and maintenance of the pump motors and valves.
- Make sure that the piping connections are supported properly and that no imposed load of piping is transferred to the pump.
- Complete all instrument mountings required as approved shop drawings.
- Complete all electrical connections to the pump motor with all necessary electrical protection and controls as per the approved electrical shop drawing.
- Complete the final alignment of the pump and motor under the manufacturer's representative’s supervision.
QUALITY CONTROL
- In general, it shall be ensured by the Site Engineer that the product manufacturer's recommendations are followed and shall be monitored by the QA/QC Engineer. However, the following points shall be ensured, in particular;
· The appropriate and approved material is used.
· The appropriate pump is used.
· Skilled labor is employed for the installation of pumps.
TESTING
- The piping connections to pumps shall be pressure tested to 1.5 times the working pressure.
- Strainer shall be cleaned after the initial flushing of the Chilled water piping system.
- Insulation of piping is to be done after pressure testing.
- Electrical circuits/controls and connections are to be checked.
INSPECTION
- An inspection request (IR) shall be raised for the consultant's inspection.
- QC inspection shall be carried out as per the installation checklist and manufacturer's instructions.
- The inspection shall be recorded in the approved format.
SAFETY
- Work will commence as per safety regulations laid down in the contract specification and project safety plan.
- Proper safety harness to be used and secured, if required.
- All personal protective equipment shall be used as appropriate according to the nature of the job.
- Housekeeping shall be of good standard, and all cut lengths and debris shall be removed.
- All lifting operations shall be monitored by the Safety Officer.
References:
MEP Planning Manual by Mr. Gulshan Kumar